Avoiding Construction Contract Cancellation costs

Though we don't normally plan to, any number of factors can lead us to cancel construction contracts. This is especially true in the construction context, where even a rainy day can cause us to halt or abandon construction entirely. If construction contracts are not carefully considered before execution, these cancellations can be extremely costly.

A recent Oregon Court of Appeals decision reminds us the myriad ways how. In Shelter Products v. Steelwood Construction, a general contractor was dissatisfied with the work of his subcontractor. Raise your hand if you can already relate.

Seeking to terminate the relationship, the general contractor looked to the terms of their contract, which provided for termination for the general contractor's convenience. This "for convenience" provision, however, was rife with terms favorable to the subcontractor.

As a result, the Court decided that when the general contractor triggered the "for convenience" termination clause, the subcontractor was then owed a litany of costs related to the work, even though it was unsatisfactory work. The Court also found the provisions of the contract did not entitle the general contractor to offset that amount with the costs incurred in repairing the defective work.

Unfortunately, contractors' work is not always going to be what we envision or expect. But, cancelling contracts when that's the case doesn't have to be a costly proposition. Parties to a contract will always demand favorable terms before coming to an agreement. When carefully drafted, however, contract terms can take the extra step of reducing costs in the event of cancellation while still being favorable to both parties. 

Even when contract terms seem clear, you should always ask an attorney to review them to prevent these and other unexpected costs.

No Comments

Leave a comment
Comment Information

Client Testimonials

  1. “Your business model is such a fresh approach to the way legal services are typically delivered.”

    President, Manufacturing
  2. “Phil will help you understand the process you are going through, and is very passionate about your needs and situation.”

    Generva
  3. “Phil, responded to my numerous questions promptly and completely. Very reasonable rates, no overbilling. Kept me informed of progress.”

    Larry
  4. “Ben legally clarified the language in my contracts without turning them into super verbose mumbo-jumbo.”

    Kevin L.
  5. “Everyone, that I've interacted with is professional, knowledgeable, forthcoming with information and educating and caring.”

    Alanna C.
SEE ALL TESTIMONIALS

111 Southwest 5th Avenue Suite 1940
Portland, OR 97204

Toll Free: 866-280-7562
Phone: 360-258-1268
Fax: 503-417-4250
Map & Directions